New contractor found to finish delayed city bridge

Work has been delayed since bankruptcy of previous builder


The city hopes the inner harbour bridge will be finished by next year (Photo: Scanpix)

February 24, 2014
18:00

by RW


DS SM, a steel supplier in Rødekro, has won the contract from the city of Copenhagen to finish the Inderhavnsbroen, a bicycle/pedestrian bridge that stretches across the inner harbour between Nyhavn and Christianshavn. The bridge was expected to be finished last year, but the bankruptcy of original contractor Pihl & Søn has kept it in limbo.

The contract is expected to be signed at the end of March. The company is engaged in analysis and optimisation of the project and the development of 3D modeling and working drawings for the steel production required to complete the project.

READ MORE: Bridges delayed after Pihl & Søn's collapse

“We narrowed the field down from six potential prospects to three,” Jens Zøfting-Larsen from the City Council told Ingeniøren newspaper. “Three contractors submitted bids based on what they thought they could finish the project for.”

Larsen said all of the bids were “close” and that the decision to go with DS SM was not based solely on price, but also the company’s reputation for patience and timeliness.

Spanish supplier sent packing
Following the Pihl ​​bankruptcy, major problems were discovered with the steel delivered by that company’s Spanish supplier. Larsen said that the city has no plans to compensate it for any losses it may have suffered when Pihl went under.

“They have contacted us, but we have consistently rejected the company on the grounds that the council had no contractual obligations to them,” said Larsen. "Any balance they are owed is part of the Pihl bankruptcy estate and they will not get much out of pursuing a case against the city of Copenhagen , because we have no obligation to them.”

The negotiations and the signing of the preliminary agreement apply only to Inderhavnsbroen. A bid to finish two other pedestrian channel bridges in the city – Trangravsbroen (over Trangraven Canal in Christianshavn) and Proviantbroen (over Fredriksholm Canal) – is expected in early March.

The city is still hoping that all of the bridges will be finished by next year. The price of completing the work on the bridges is estimated to be 66 million kroner.



Related stories



Latest Comments

I know a few Danes that were deported from the states so i support this. ;-)

(Juliousbass "the Future of Bass" on October 22, 2014 21:00)

Culture vultures

(Juliousbass "the Future of Bass" on October 22, 2014 20:55)

This is so cool. Funerals with the horse drawn hearses are always so sad &...

(Buzzy Sørensen on October 22, 2014 15:39)

Fraud seems to be an integral part of the Vestas business model. Allegations...

(Bill Jones on October 22, 2014 14:05)

This Brit has a long way to go before he is integrated in Denmark, and...

(Nicholas Gunder on October 22, 2014 13:43)

He has to defend a 12000 DKK spend? That is a joke.

(Andrei Grigorian on October 22, 2014 12:50)

I am against the new rules . It will destroy lots of green card holders life

(Sumon Das on October 22, 2014 10:54)

Ebola is a serious threat to the health and well-being of people aroubd the...

(Calvin Bernhardt on October 22, 2014 10:26)

Prayers to the families.

(Calvin Bernhardt on October 22, 2014 10:19)

Sad, but still a reality in Naestved.

(Calvin Bernhardt on October 22, 2014 10:10)