“Completely unrealistic” that Metro expansion will be done on time

With noise complaints and inadequate equipment, three former employees of project’s lead contractor say expansion delays are a certainty

According to three independent sources, a combination of poor planning, inept leadership and a too low project bid means that the ongoing Metro construction is already significantly behind schedule and will face further delays.

“It’s common knowledge throughout the organisation that the project is delayed for two years,” one anonymous source told Politiken newspaper. “2018 was earmarked as a buffer for the schedule, but that is gone now and it is completely unrealistic that the Metro City Ring will be finished by then.”

The three sources, who have all be employed by the expansion project’s leading contractor, CMT, argued that the leadership reacted far too late to the discovery that the machinery being used in the project can't properly drill in the hard Copenhagen underground.

Noise complaints bogged them down
But Henrik Plougmann Olsen, the head of Metroselskabet, the company that operates the Metro, was adamant that the original schedule will hold true.

“If you disregard the uncertainty that arose with the current processing of complaints by [the environment appeals board] Natur- og Miljøklagenævnet, we still expect to open by December 2018,” Olsen wrote in an email to Politiken.

Copenhagen's mayor, Frank Jensen (Socialdemokraterne), also shifted the blame of potential delays onto the noise complaint processing that has shut down or hampered construction at several Metro construction sites.

A number of sites face delays
After comparing the original plans from four of the construction sites from 2011 with Metroselskabet’s updated time schedule, Politiken concluded that the construction faces delays of up to a year.

The site at Nørrebroparken was due to begin tunnel drilling in October 2012, but the site is still in the testing phase. Problems at the Marmorkirken site mean that the tunnelling work will face additional eight-month delays.

Sites at Frederiksberg Allé and Copenhagen Central Station are also facing delays.

Experts point to investment issues
International experts point to a postponement in larger investment in the City Ring budget as a clear indication of increased risk of delays to the construction.

A four billion kroner investment has been postponed to the last four years of the construction and in 2017 alone, which was originally to be used for testing the train system, 2.2 billion kroner will be invested in the project.

“That means that there is no room even for small errors and problems if they hope that the project will be finished on time and the budget will be kept,” Terry Williams, a professor and dean at Hull University Business School in the United Kingdom, told Berlingske newspaper.

Metroselskabet continues to stand by its original pledge that the City Ring will open in December 2018 at a price of 21.3 billion kroner.




  • Diplomatic tensions between US and Denmark after spying rumors

    Diplomatic tensions between US and Denmark after spying rumors

    A Wall Street Journal article describes that the US will now begin spying in Greenland. This worries the Danish foreign minister, who wants an explanation from the US’s leading diplomat. Greenlandic politicians think that Trump’s actions increase the sense of insecurity

  • Diplomacy meets Westeros: a dinner with the King, Queen – and Jaime Lannister

    Diplomacy meets Westeros: a dinner with the King, Queen – and Jaime Lannister

    What do King Frederik X, Queen Mary, UN Secretary-General António Guterres, and Jaime Lannister have in common? No, this isn’t the start of a very specific Shakespeare-meets-HBO fanfiction — it was just Wednesday night in Denmark

  • Huge boost to halt dropouts from vocational education

    Huge boost to halt dropouts from vocational education

    For many years, most young people in Denmark have preferred upper secondary school (Gymnasium). Approximately 20 percent of a year group chooses a vocational education. Four out of 10 young people drop out of a vocational education. A bunch of millions aims to change that

  • Beloved culture house saved from closure

    Beloved culture house saved from closure

    At the beginning of April, it was reported that Kapelvej 44, a popular community house situated in Nørrebro, was at risk of closing due to a loss of municipality funding

  • Mette Frederiksen: “If you harm the country that is hosting you, you shouldn’t be here at all”

    Mette Frederiksen: “If you harm the country that is hosting you, you shouldn’t be here at all”

    With reforms to tighten the rules for foreigners in Denmark without legal residency, and the approval of a reception package for internationals working in the care sector, internationals have been under the spotlight this week. Mette Frederiksen spoke about both reforms yesterday.

  • Tolerated, but barely: inside Denmark’s departure centers

    Tolerated, but barely: inside Denmark’s departure centers

    Currently, around 170 people live on “tolerated stay” in Denmark, a status for people who cannot be deported but are denied residency and basic rights. As SOS Racisme draws a concerning picture of their living conditions in departure centers, such as Kærshovedgård, they also suggest it might be time for Denmark to reinvent its policies on deportation

Connect Club is your gateway to a vibrant programme of events and an international community in Denmark.